32
The most comprehensive Oracle applications & technology content under one roof Capital Projects Risk Development and Management Christiane Kampschulte Parsons Brinckerhoff 16 th August 2010 2:30-3:15pm

C:\documents and settings\ckampschulte\desktop\in sync risk range analysis

Embed Size (px)

DESCRIPTION

 

Citation preview

Page 1: C:\documents and settings\ckampschulte\desktop\in sync risk range analysis

The most comprehensive Oracle applications & technology content under one roof

Capital ProjectsRisk Development and Management

Christiane KampschulteParsons Brinckerhoff

16th August 2010 2:30-3:15pm

Page 2: C:\documents and settings\ckampschulte\desktop\in sync risk range analysis

Introduction

• The presentation addresses Risk management in terms of quantitative Risk Management not qualitative scoring methods.

• The presentation compares two projects.

• To validate the effectiveness of Risk Management statistically we require more examples and case studies.

• None of the Project are as per “Best Practice” which is dealt with at the end.

Page 3: C:\documents and settings\ckampschulte\desktop\in sync risk range analysis

Introduction

• There are a number of uncertainties in every project that have a potential to affect the outcome.

• Commonly, the provision for these uncertainties is taken care of by adding a percentage of costs as contingency to the cost estimate and adding a time contingency at the end of the longest path.

Page 4: C:\documents and settings\ckampschulte\desktop\in sync risk range analysis

Introduction

The paper compares 2 similar projects and:

• Highlights the importance of calculating and documenting a meaningful cost and schedule contingency.

• Illustrates the benefits of project cost and time estimate range reviews.

Page 5: C:\documents and settings\ckampschulte\desktop\in sync risk range analysis

CASE STUDY A :

Mining Infrastructure Project

in Western Australia

Page 6: C:\documents and settings\ckampschulte\desktop\in sync risk range analysis

CASE STUDIES

Rail Construction TD-Graph

-20

10

40

70

100

130

160

190

220

250

6-Ap

r-07

1-Ju

n-07

27-J

ul-0

7

21-S

ep-0

7

16-N

ov-0

7

11-J

an-0

8

7-M

ar-0

8

2-M

ay-0

8

27-J

un-0

8

Chai

nage

(km

)

Capping Tracklaying Bridges Commissioning ActivitiesTarget Track Actual Track Layed Hand Lay2

Bridge 1

Bridge 2

Bridge 4

Bridge 3

Bridge 5

Bridge 7

Bridge 6

Hand layed Cloud Break

TargetNo Later then

date

Actual Track

LayedHand layed Loop

PORT

COMMISSIONING &

Stockpiling

Bridge 8

Page 7: C:\documents and settings\ckampschulte\desktop\in sync risk range analysis

• Cost and time estimates were based on information given by Engineering Design Team.

• The project started with a single point cost and time estimate.

• The single point estimate resulted in a contingency linked to the time and cost estimate. This was a fixed percentage added to the cost estimate and a fixed number of days added to the project programme.

Case A

Page 8: C:\documents and settings\ckampschulte\desktop\in sync risk range analysis

• Execution phase risk management workshops were conducted at regular intervals but inputs were taken from a Safety perspective and risk were not quantified.

• The contractors were required to submit a time scaled detailed network program, hours spent and forecasts.

• No alliance partner's forecast showed schedule or cost overrun. Schedule updates always showed a date within the required dates.

Case A

Page 9: C:\documents and settings\ckampschulte\desktop\in sync risk range analysis

• Variations were approved while the cost value did not surpass the project single point estimate.

• No other number than the original estimate was ever communicated for time and cost.

Case A

Page 10: C:\documents and settings\ckampschulte\desktop\in sync risk range analysis

• The project was being built in a Cyclone prone area and was under a high cyclone danger zone. A cyclone hit the area and one of the 3 worker accommodation camps a was damaged.

Case A

Page 11: C:\documents and settings\ckampschulte\desktop\in sync risk range analysis

• This incident triggered the intensive review of the project’s time estimate and cost estimate with focus on the assumptions made for calculating the contingency.

• The finding were that the scope hat deviated from the initial estimate.

• The assumptions made for the calculation of time and cost contingency were not treaceable so couldn’t not be evaluated for their adequateness.

Case A

Page 12: C:\documents and settings\ckampschulte\desktop\in sync risk range analysis

CASE STUDY B :

Coal Terminal Project

in New South Wales

Page 13: C:\documents and settings\ckampschulte\desktop\in sync risk range analysis
Page 14: C:\documents and settings\ckampschulte\desktop\in sync risk range analysis

• A Range Analysis Workshop (RAW) was held to identify and quantify all risks and uncertainties that could cause a deviation to the estimate.

• Particular attention was paid to the facilitation of this workshop where project participants were encouraged to come up with extreme outcomes of the uncertainties.

Case B

Page 15: C:\documents and settings\ckampschulte\desktop\in sync risk range analysis

Examples for risk sources considered in the RAW were:• Availability of area or facility, staff availability and major

equipment.

• Uncertainty over productivity level on the project.

• Adverse environmental conditions

• Specific risks identified for the project that have the potential to impact the project like geotechnical conditions, Industrial Relations, Quality.

Case B – Risk sources

Page 16: C:\documents and settings\ckampschulte\desktop\in sync risk range analysis

• For awarded contracts, capital cost sources that were considered were

– uncertainty associated with variations that have been submitted, – uncertainty with forecast variation and – uncertainty associated with emerging trends.

Case B - Risk sources

Page 17: C:\documents and settings\ckampschulte\desktop\in sync risk range analysis

Capital cost inputs that were considered for un-awarded contracts typically included

– variations in project scope that were being developed at that stage, – variations in unit rates considering the time lag between feasibility study

and project execution, – variations in quantities-both materials and work hours which are impacted

by the stage of the design process and – risk events specific to the project.

Case B - Risk sources

Page 18: C:\documents and settings\ckampschulte\desktop\in sync risk range analysis

• The schedule risk profile was developed through a summary risk schedule developed from the project schedule that captured the key milestones and the associated near critical activities.

• Duration ranges were developed for these activities in a facilitated workshop. These ranges were defined by the minimum case, maximum case, P10, P90 scenarios and probability of achieving or improving the task duration.

• The ranges were then used to develop a probability distribution for the activity. Correlations between the ranged schedule activities were also included.

Case B – Schedule range analysis

Page 19: C:\documents and settings\ckampschulte\desktop\in sync risk range analysis

Case B – Schedule range analysisKey Drivers of the Project completion milestone

8%

9%

9%

9%

12%

16%

16%

17%

26%

38%DS80 - Civil Works - Dump Station

W110 - Marine Piling Works

SM10 - Dumpstation Structural Mechanical

EL40 - Precommission Wharf Area

SL40 - Load Commission Ship Loader

W70 - Fab/ Erection Main Structural Works in SEP 1

EL50 - Commission Coal Inbound

EL10 - Install Electrical Services Dumpstation

EL30 - Install Electrical Services - Wharf Area

OB10 - Wharf Civil Works, Structural and Buffer Bin

Project Complete Milestone - Schedule Sensitivity Index

Page 20: C:\documents and settings\ckampschulte\desktop\in sync risk range analysis

• Awarded contracts – models cost uncertainty due to variations.• Un-awarded contracts – modeled uncertainty associated with the

estimate of these contracts.• Owners – models uncertainty associated with owner’s costs.• Project Risks – models the risks that have been identified.• Project Scope – models potential scope changes for the project.• Schedule – models the time variable uncertainty associated with

schedule duration risk.

 

Case B – CAPEX range analysis

Page 21: C:\documents and settings\ckampschulte\desktop\in sync risk range analysis

Case B - CAPEX Range analysis

Schedule range analysis

Cost range analysis

Page 22: C:\documents and settings\ckampschulte\desktop\in sync risk range analysis

RiskModel

Input risk events & responses – risk register

Input estimate risk ranges & correlations for key elements Minimum Most Likely Maximum

Min Max

ML

Input Schedule risk events & responses

Key Capital Risk Drivers At WBS Level

Equipment

Bulk Materials

Freight

Owner's Costs

EPCM Cost

Labour

ONESTEEL - Whyalla ProjectsTotal Project Capital Risk profile

8 8.5 9 9.5 10 10.5 11 11.5 12 12.5 13 13.5 14

Capital cost ($M)

Base Estimate$9.65M

Mean or Expected Cost = $10.82MP5 = $9.65MP95 = $12M-10.8% 11%

P75 = $11.3M

Contingency @ Mean = $1.17M

WBS Risk 699,158$

Project Risk 266,761$

Schedule risk 201,667$

Contingency @Mean 1,167,586$

Contingency @ Mean Break-up

Contingency @ P75 = $1.65M

RiskModel

Input risk events & responses – risk register

Input estimate risk ranges & correlations for key elements Minimum Most Likely Maximum

Min Max

ML

Input Schedule risk events & responsesRisk

ModelRisk

Model

Input risk events & responses – risk register

Input estimate risk ranges & correlations for key elements Minimum Most Likely Maximum

Min Max

ML

Input Schedule risk events & responses

Input risk events & responses – risk register

Input estimate risk ranges & correlations for key elements Minimum Most Likely Maximum

Input estimate risk ranges & correlations for key elements Minimum Most Likely Maximum

Min Max

ML

Input Schedule risk events & responses

Key Capital Risk Drivers At WBS Level

Equipment

Bulk Materials

Freight

Owner's Costs

EPCM Cost

Labour

ONESTEEL - Whyalla ProjectsTotal Project Capital Risk profile

8 8.5 9 9.5 10 10.5 11 11.5 12 12.5 13 13.5 14

Capital cost ($M)

Base Estimate$9.65M

Mean or Expected Cost = $10.82MP5 = $9.65MP95 = $12M-10.8% 11%

P75 = $11.3M

Contingency @ Mean = $1.17M

WBS Risk 699,158$

Project Risk 266,761$

Schedule risk 201,667$

Contingency @Mean 1,167,586$

Contingency @ Mean Break-up

Contingency @ P75 = $1.65M

Case B - Risk model

Capital Cost

P95P5Mean

Key Capital risk drivers

Page 23: C:\documents and settings\ckampschulte\desktop\in sync risk range analysis

CASE A CASE B

Expectation on a single project end date Provides a range of dates with quantified probability

Identifies the Critical Path Identifies important areas of the project which might not necessarily be the critical path

Developing a schedule and working to it Developing live Project Execution Plans

Risk Management not integrated with schedule and budget

Integrated Risk Management with time and cost estimate

The schedule and cost estimate are looked into separately.

The risk management process integrates the schedule, cost and the risk register.

Fear of providing surprising “bad news” to the top management

Providing a range of estimates to the top management to avoid surprises.

Differences

Page 24: C:\documents and settings\ckampschulte\desktop\in sync risk range analysis

• One definition of an estimate is that it is the expected value of

a complex equation of probabilistic elements, each subject to random variation within defined ranges. Ref: Larry R.Dysert, CCE. Skills and Knowledge of Cost

Engineering. 5th Edition Revised p 9.21, AACE International, 2007

• The outputs are only as good as their inputs

What do the cases illustrate?

Page 25: C:\documents and settings\ckampschulte\desktop\in sync risk range analysis

Integrated cost-schedule risk analysis

The purpose of this is to estimate the appropriate level of cost contingency reserve on projects and also to include the impact of schedule risk on cost risk.

Best Practice (as per AACE recommendation)

Page 26: C:\documents and settings\ckampschulte\desktop\in sync risk range analysis

• Start with a “good” logic driven schedule (summary schedule)• Assign cost loaded resources to the activities in the schedule• Take a risk driven approach. Use the “Risk Register”.• Collect good risk data from facilitated workshop or one to one

interview with stakeholders or project participants. • Derive contingency reserve of time and cost, prioritize the

risks and mitigating them in steps.

Best Practice

Page 27: C:\documents and settings\ckampschulte\desktop\in sync risk range analysis

1. Risks are identified during a qualitative risk analysis of the project. This leads to a list of prioritized risks which are characterized by their probability and impact ranges.

2. A best practice project schedule which is resource loaded.

3. The “Neat Estimate” (an estimate without contingency) assigned to the activities in the schedule.

Best Practice - Inputs

Page 28: C:\documents and settings\ckampschulte\desktop\in sync risk range analysis

From the inputs, a risk model would be created in a readily available software like “Primavera Risk Analysis V8” (Pertmaster) ready to run a number of iterations simulating the project

Risk # 01 – P50% Factors

0.95,1.05,1.15

Activity A Activity B

Best Practice - Model

Page 29: C:\documents and settings\ckampschulte\desktop\in sync risk range analysis
Page 30: C:\documents and settings\ckampschulte\desktop\in sync risk range analysis

Outputs

21-Dec-12 05-May-14

Distribution (start of interval)

0

100

200

300

400

500

600

700

Hit

s

0% 19-Dec-12

5% 27-Apr-13

10% 25-May-13

15% 13-Jun-13

20% 03-Jul-13

25% 18-Jul-13

30% 01-Aug-13

35% 14-Aug-13

40% 28-Aug-13

45% 08-Sep-13

50% 20-Sep-13

55% 02-Oct-13

60% 16-Oct-13

65% 29-Oct-13

70% 14-Nov-13

75% 30-Nov-13

80% 16-Dec-13

85% 06-Jan-14

90% 03-Feb-14

95% 23-Mar-14

100% 02-Dec-14

Cu

mu

lati

ve F

req

uen

cy

AACEI Integrated Cost-Schedule RiskEntire Plan : Finish Date

$600,000 $800,000 $1,000,000

Distribution (start of interval)

0

200

400

600

800

Hit

s

0% $537,199

5% $619,334

10% $636,168

15% $648,572

20% $658,705

25% $667,247

30% $675,521

35% $683,271

40% $692,139

45% $699,319

50% $706,146

55% $713,313

60% $721,955

65% $730,838

70% $740,066

75% $749,866

80% $760,750

85% $775,498

90% $792,533

95% $819,295

100% $1,008,966

Cu

mu

lati

ve F

req

uen

cy

AACEI Integrated Cost-Schedule RiskEntire Plan : Cost

Page 31: C:\documents and settings\ckampschulte\desktop\in sync risk range analysis

Answers we get

1. Which risks are most important to the achievement of the project schedule and cost estimate?

2. How likely are the project plan’s cost and schedule targets to be met - taking into account the risk that may affect that plan? 

3. How much contingency of time and cost needs to be provided to meet the risk threshold of the project management or other stakeholders? 

Page 32: C:\documents and settings\ckampschulte\desktop\in sync risk range analysis

Tell us what you think…

• http://feedback.insync10.com.au

• Questions to : [email protected] [email protected]