127
FPSO DESIGN- AN INTRODUCTION Kamal K. Ravi Engineering Projects& System Manager PTSC M&C

0020 introduction to fpso design

  • View
    1.379

  • Download
    40

Embed Size (px)

DESCRIPTION

 

Citation preview

Page 1: 0020 introduction to fpso design

FPSO DESIGN- AN INTRODUCTION

Kamal K. Ravi

Engineering Projects& System Manager PTSC M&C

Page 2: 0020 introduction to fpso design

Introduction to Floating Production Systems

Chapter 1

Page 3: 0020 introduction to fpso design

Floating Production Systems

• Classified as:

Semi-submersible and tension leg platforms

- Little or no storage capacity

Spars

- Limited storage capacities

FPSO – primarily mono-hull vessel

Page 4: 0020 introduction to fpso design

Typical View of an FPSO

Page 5: 0020 introduction to fpso design

Water Depth and Sea States • Water depths

Shallow

-Less than 50m

Moderate

-Down to 300m

Deep

-Down to 1500m

Ultra Deep

-Beyond 1500m

• Sea states

Benign

-Hs 0 to 4.0m

Medium

-Hs 4.0 to 9.0m

Severe

-Hs 9.0 to 14.0m+

Hs=significant wave

height

Page 6: 0020 introduction to fpso design

FPS Application Chart

Page 7: 0020 introduction to fpso design

History of the FPSO

• 1977 First FPSO- Castellon Field

Offshore Spain

Mooring –SALM

Water dept 117m

• During 1980s

Moderate depths

Benign waters

Cost effective solution

- For marginal fields

Proven safety record

Page 8: 0020 introduction to fpso design

History of the FPSO

• During 1990s

- Deeper waters

- Rougher seas

- Black oil reservoirs

• Early 21st Century

-Ultra deep waters

-Large numbers of risers

-Very high throughputs

-Storage – VLCC Class

-Newly built vessels

-Handle gas liquids

Page 9: 0020 introduction to fpso design

The Pros and Cons

• Advantages

- Utilises existing ships

- Faster development

- Reduced upfront costs

- Early cash flow

- Re-usable

- Higher residual value

- Lower abandonment costs

• Disadvantages

- No drilling

- Subsea wells only

- Rushed design can lead to mistake

- Weather dependency

- Production

- Offtake

Page 10: 0020 introduction to fpso design

What is an FPSO?

• F = Floating – it looks like a ship – but is it?

• P = Production - Produces and processes a reservoir fluid

• S = Storage – Vessel’s cargo tanks store product crude

• O = offtake – Crude is offloaded to shuttle tanker

• That is the Simple Look

Page 11: 0020 introduction to fpso design

Mooring the FPSO

• An FPSO is essentially a ship permanently moored on the open ocean

• Stresses imposed on the hull need to be minimised

• Ship has to survive for life of project

• Weathervaning is a natural effect which minimises stressess

• Allows ship to align itself with the wind, wave and current

• Turret mooring allows weathervaning

Page 12: 0020 introduction to fpso design

Cargo Handling on FPSO

• An FPSO is a crude oil tanker

• Two issues are critically important

Loading and offloading the cargo

- Creates stresses on hull- have to be minimised

-Achieved by load monitoring and ballast system

Storing the product crude safely

- Cargo tank atmosphere potentially explosive

- Tanks must remain “inerted” at all times

- Achieved by use of inert gas system (IGS)

Page 13: 0020 introduction to fpso design

Production and Processing on FPSO

• Two issues important Sustaining and optimising reservoir productivity - Sustaining reservoir pressure - Optimising reservoir flow - Assurance of flow from reservoir to processign centre Safe, efficient and effective processing - Maximising liquids recovery - Disposal of gas safety and economically - Treatment and disposal of produced water - Efficient use of chemicals to aid both production and

processing

Page 14: 0020 introduction to fpso design

FPSO Design Issues

• Main Technical Questions

Selection of the mooring system

- Predominantly turret mooring, but spread mooring and yoke mooring also used

Location of the accommodation block

- Conventionally at aft end of ship

- New build vessels may have forward accommodation

Process plant layout, based on safety and operability

Page 15: 0020 introduction to fpso design

Turret Mooring System

• Mooring turret is unique FPSO feature

• Serves three purposes:

Anchors vessel at geo-stationary position

Allows vessel to weathervane

Provides conduit for fluid transfer

- Subsea reservoir infrastructure to

topside processing plant

Page 16: 0020 introduction to fpso design

Turret Designs

Turret designs based on location

- Either external to the hull of the vessel

- Or internally fitted inside the hull

Choice based on:

- Geographical location

* Sea states, strom systems, ice, etc

- Water depth

- Number of fluid transfer risers

Page 17: 0020 introduction to fpso design

External Turret Design

Page 18: 0020 introduction to fpso design

Spread Mooring

Page 19: 0020 introduction to fpso design

Buoy Yoke Mooring

Page 20: 0020 introduction to fpso design

Jacket Soft Yoke Mooring

Page 21: 0020 introduction to fpso design

Jacket Soft Yoke Mooring

Page 22: 0020 introduction to fpso design

Internal Turret Design (Tentech)

Page 23: 0020 introduction to fpso design

Detail of Internal Turret

Page 24: 0020 introduction to fpso design

Large Internal Turret

Page 25: 0020 introduction to fpso design

Disconnectable External Turret

Page 26: 0020 introduction to fpso design

Disconnectable Internal Turret

Page 27: 0020 introduction to fpso design

Location of Accommodation

• Largely influenced by position of turret

• Research shows that turret should be on further aft than 19% of length of vessel

• Achieves optimal operational efficiency

- Maximises weathervaning

- Minimises “pitching” effect

• May exlude choice in placement of accommodation

Page 28: 0020 introduction to fpso design

Accommodation in Aft Location

• Normal solution for ship conversions

• Allows for optimal positioning of turret

• Stern abandonment is safest option

• Crew downwind of fire / smoke / flame

Additional engineering may be needed

- To protect “safe refuge’

- To allow for helicopter operations

- To minimise flare radiation effects

Page 29: 0020 introduction to fpso design

Tantawan Explorer Aft Accommodation

Page 30: 0020 introduction to fpso design

FPSO Firenze – Italy Aft Accommodation

Page 31: 0020 introduction to fpso design

Accommodation in in Forward Location

• Most applicable for new build FPSOs

• Turret is aft of accommodation

• Crew upwind of fire / smoke / flame

• Forward abandonment may be difficult in rough weather

• Motion effects may make living conditions uncomfortable for crew

Page 32: 0020 introduction to fpso design

Accommodation – Forward FPSO Norne

Page 33: 0020 introduction to fpso design

Accommodation – Forward FPSO Asgard A

Page 34: 0020 introduction to fpso design

Number of FPSOs Built

Page 35: 0020 introduction to fpso design

Process Plant Layout

• Layout based on

-Safety

-Operability

• Most hazardous process areas

-Furthest from accommodation (TSR)

• Critical Level control

-Close to midships

Page 36: 0020 introduction to fpso design

Distribution of FPSOs Worldwide (2008)

Page 37: 0020 introduction to fpso design

Recent FPSO Developments (2000-2010)

• West Africa - Serpentina, Mystras, Sanha, Kizomba,AKPO - USAN • Brazil - Espadarte, Brasil • Australasia - Northern Endeavour, Venture 11 • South East Asia - Su Tu Den • Canada - Terra Nova

Page 38: 0020 introduction to fpso design

FPSO Systems

Chapter 2

Page 39: 0020 introduction to fpso design

FPSO Building Blocks

• Main systems for FPSO are:

- Hull type

- Oil storage

- Moorings

- Fluid transfer

- Topsides process plant

- Offtake and export

- Accommodation

Page 40: 0020 introduction to fpso design

Hull Types

• Classic hull type for FPSO:

- Mono-hull, crude carrier classification

- Segregated ballast

- Mono-hull meaning single steel shell

- Double- hull not standard requirement

- Exceptions – GoM, NWS Australia

• Hull can be either:

- Existing carrier- suitable for conversion

- Newly built specifically for FPSO service

Page 41: 0020 introduction to fpso design

Tanker Conversion

Page 42: 0020 introduction to fpso design

Conversion Installing Topsides Modules

Page 43: 0020 introduction to fpso design

New Built Hull

Page 44: 0020 introduction to fpso design

Northern Endeavour New-Build

Page 45: 0020 introduction to fpso design

Moorings

• The moorings for an FPSO can be:

- Spread moorings

- Benign conditions

- Any water depth

- Jacket or tower moorings

- Moderate conditions

- Shallow waters

- Turret moorings

- Any conditions and water depth

Page 46: 0020 introduction to fpso design

The External Turret System

Page 47: 0020 introduction to fpso design

Simple External Turret

Page 48: 0020 introduction to fpso design

Large External Turret

Page 49: 0020 introduction to fpso design

Disconnectable External Turret

Page 50: 0020 introduction to fpso design

Internal Turret System

Page 51: 0020 introduction to fpso design

Internal Turret

Page 52: 0020 introduction to fpso design

Fluid Transfer System

• Function of system: - To connect subsea risers to topsides process plant • Fact - Risers are stationary pipes - Topsides plant is on weathervaning ship • Problem - How to connect the two • Answer - Fluid swivel

Page 53: 0020 introduction to fpso design

Fluid Swivels

• Predominant fluid transfer system is the fluid swivel

• Commonly referred to as the radial swivel joint

• The term toroidal swivel is used to describe shape of fluid pathway

Page 54: 0020 introduction to fpso design

Radial Swivel Joint

Page 55: 0020 introduction to fpso design

Moorings and Fluid Transfer

• Fluid swivels only required for:

- Turret moorings

- Jacket moorings

• Spread moored FPSOs:

- Do not rotate around mooring point

- Do not require swivel joints

Page 56: 0020 introduction to fpso design

Topsides Process Plant

• Processing which occurs on an FPSO:

- Three phase separation of the well fluids

- Gas recompression

- Gas treatment

- Produced water treatment

- Injection water treatment

• Standard black oil processing

- Practiced worldwide

Page 57: 0020 introduction to fpso design

Offtake and Export

• Crude oil export from an FPSO

- Connection to a pipeline

- Direct ship transfer

- Using a surface hose either floating or reeled

- Transfer through a loading buoy

Page 58: 0020 introduction to fpso design

Direct Ship to Ship Offtake

Page 59: 0020 introduction to fpso design

CALM Loading Buoy

Page 60: 0020 introduction to fpso design

Accommodation • Two possible locations - Bow or Stern • Accommodation block contains temporary safe

refuge (TSR) • Layout of topsides plant must be based on: - Survivability of TSR

Greatest risks remote Gas or smoke ingression via HVAC prevented Fire and blast-proofing may need to be upgraded

- Unhindered personnel access to TSR from any point on deck

Page 61: 0020 introduction to fpso design

Cost Estimate Conceptual Design- Large FPSO

Page 62: 0020 introduction to fpso design

Turret and Mooring Systems Design

Chapter 3

Page 63: 0020 introduction to fpso design

Turret Mooring System

• Mooring turret is unique FPSO feature

• Serves three purposes:

- Anchors vessel at geo-stationary position

- Allows vessel to weathervane

- Provides conduit for fluid transfer

Subsea reservoir infrastructure to topside processing plant

Page 64: 0020 introduction to fpso design

Turret Overview

Page 65: 0020 introduction to fpso design

Turret Design

• Three types of turret mooring systems

- External

- Internal

- Submerged

• Each type can be sub-divided into:

- Disconnect type

- Permanent connect type

Page 66: 0020 introduction to fpso design

Disconnectable External Turret

Page 67: 0020 introduction to fpso design

External Turret Permanent Mooring

Page 68: 0020 introduction to fpso design

External Turret – Permanent Moored

Page 69: 0020 introduction to fpso design

Internal Permanently Moored Turret

Page 70: 0020 introduction to fpso design

Internally Permanently Moored Turret

Page 71: 0020 introduction to fpso design

Maersk Curlew FPSO Turret - 1996

Page 72: 0020 introduction to fpso design

Maersk Curlew FPSO

Page 73: 0020 introduction to fpso design

FPSO Anasuria Turret Manifold Decks

Page 74: 0020 introduction to fpso design

Large Diameter Internal Turrets

Page 75: 0020 introduction to fpso design

Small Diameter Turrets

Page 76: 0020 introduction to fpso design

Internal (Submerged) Disconnect Turret

Page 77: 0020 introduction to fpso design

Submerged Turret

Page 78: 0020 introduction to fpso design

Spread Moorings

Page 79: 0020 introduction to fpso design

Bow Anchoring for Spread Mooring

Page 80: 0020 introduction to fpso design

Jacket or Tower Mooring

Page 81: 0020 introduction to fpso design

Tower Mooring

Page 82: 0020 introduction to fpso design

Ship’s Motion

Page 83: 0020 introduction to fpso design

Vessel Motion across the Sea Surface

• Based on the period » Short period motion due to waves

– 6 to 20 second typically

» Longer period due to wind and waves – Can be several minutes

– This is weathervaning

• Mooring forces increase with motion » In other words in rougher the seas the greater are

the mooring forces – More or stronger anchors

Page 84: 0020 introduction to fpso design

Mooring Chain Table

Page 85: 0020 introduction to fpso design

FPSO Mooring Spreads

Page 86: 0020 introduction to fpso design

Process Facilities

Chapter 4

Page 87: 0020 introduction to fpso design

Processing Facilities on a Typical FPSO

• Functional requirements

» Oil /gas separation

» Gas compression and treatment

» Produced water treatment and disposal

» Water injection

» Gas export / re-injection

» Support utilities

» Chemical injection and distribution

Page 88: 0020 introduction to fpso design

Oil /Gas Separation

• First stage HP separation

• Second stage MP separation

• Third stage LP separation

• Electrostatic coalescing

• Well test separation

Page 89: 0020 introduction to fpso design

Oil / Gas Separator with Wave Motion Internals

Page 90: 0020 introduction to fpso design

Overall Topsides Module Layout

Page 91: 0020 introduction to fpso design

Gas Compression & Treatment

• The three compression stages and associated compressors are:

» Flash gas compression K-201

» MP gas compression K-202

» HP gas compression K-203

Page 92: 0020 introduction to fpso design

Water Injection

• Seawater supply

• Vacuum de-aeration

• Chemical injection

• Injection water delivery

Page 93: 0020 introduction to fpso design

Support Utilities

• Fuel gas

• Flare & drainage

• Compressed air system

• Heating medium system

• Cooling medium system

• MP steam

• Seawater system

• Chemical injection system

• Power generation

Page 94: 0020 introduction to fpso design

Utilities Integration Diagram

Page 95: 0020 introduction to fpso design

Chemical Injection System

• Consists of three sub-systems

» Topsides

– For oil / gas & injection water processing & protection

» Hydrate inhibition

– For production & gas processing

» Subsea

– For wellhead & flowline protection

Page 96: 0020 introduction to fpso design

Safety Assessment

• Need to consider

» Layout of equipment

» Consequences of fire / explosion

» Safety venting

» Design of the fire system

» Containment & drainage of process fluids

Page 97: 0020 introduction to fpso design

Alternative Technologies

• Multi-phase flow metering

• Subsea water separation

• Subsea raw water injection

• Multi-phase booster pumping

• Subsea power distribution

Page 98: 0020 introduction to fpso design

An SBM Vessel

Page 99: 0020 introduction to fpso design

Power Generation Module

Page 100: 0020 introduction to fpso design

Utilities (CM+HM) Module

Page 101: 0020 introduction to fpso design

Water Injection Pumps

Page 102: 0020 introduction to fpso design

Water Injection Module

Page 103: 0020 introduction to fpso design

Chemical Injection & Water Injection

Page 104: 0020 introduction to fpso design

Oil / Gas Separation Module

Page 105: 0020 introduction to fpso design

Methanol Storage & Injection

Page 106: 0020 introduction to fpso design

Glycol Regeneration

Page 107: 0020 introduction to fpso design

Flare K.O Drums

Page 108: 0020 introduction to fpso design

End of a Hard Day’s Work

Page 109: 0020 introduction to fpso design

Mess Hall

Page 110: 0020 introduction to fpso design

Gourmet Kitchen

Page 111: 0020 introduction to fpso design

Her Own Power

Page 112: 0020 introduction to fpso design

Marine Systems

Chapter 5

Page 113: 0020 introduction to fpso design

Marine Systems

• Choice of Ship

• Tank Arrangements

• Loading/Offloading System

• Cargo Pumps

• Ballast System

• Stops System

• Inert Gas System

• Vessel/Topsides Interface

Page 114: 0020 introduction to fpso design

Choice of Ship

• Factors affecting the choice of ship are:

» Cost of conversion vs new build

» Field life and redeployment

» Need for additional strengthening

» Cargo tank conditions

• Capacity of cargo storage and offloading

• Condition of machinery

• Propulsion type

• Free area for topsides plant

Page 115: 0020 introduction to fpso design

Vessel Sizes

• Tanker sizes used for FPSO conversion

» VLCC (very large crude carrier)

– 200,000 to 319,000 dwt

» Suezmax

• 120,000 to 200,000 dwt

» Aframax

• 75,000 to 120,000 dwt

Page 116: 0020 introduction to fpso design

FPSO Tank Arrangements

Page 117: 0020 introduction to fpso design

Cargo Offloading Systems

• Floating Hose

• Reeled Hose

• CALM Buoy

• Submerged Hose

Page 118: 0020 introduction to fpso design

Floating Hose Arrangement

Page 119: 0020 introduction to fpso design

FPSO Stern Offloading

Page 120: 0020 introduction to fpso design

Stern Offloading Hose Reel

Page 121: 0020 introduction to fpso design

Reeled Hose Arrangement

Page 122: 0020 introduction to fpso design

CALM Buoy

Page 123: 0020 introduction to fpso design

Submerged Hose System

Page 124: 0020 introduction to fpso design

Submerged Cargo Pumps

Page 125: 0020 introduction to fpso design

Tank Cleaning

• Crude Oil Washing – COW

» Removes wax and sediment build-up

» Carried out during offloading operations

» Uses warmed crude oil

» Following oil washing

– Water washing used prior to tank inspection

– Water washing can generate static charges

– Always done under inert gas blanket

Page 126: 0020 introduction to fpso design

Tank Vapour Recovery

• Today’s environment focus is on:

» Emissions!!

• Cargo tank operations – no exception

• Tank vapour recovery is modern trend

» Don’t vent tank vapour – re-use it!!

• Problem – its “inert” nature

• Answer – don’t use “inert” gas

Page 127: 0020 introduction to fpso design

Tank Blanketing

• Latest development is tank blanketing

» Use a gas that will:

– Exclude air, but be re-usable

» Hydrocarbon gas fills that need

• During loading tank gases

» Recovered for use as fuel

• During offloading separator gas

» Flows into tanks to exclude air