Jeff Armstrong - DAC International Division Kott Group Cold Climate Social Housing - a case study

Sdrhcon2011 armstrong

Embed Size (px)

DESCRIPTION

 

Citation preview

Page 1: Sdrhcon2011 armstrong

Jeff Armstrong - DAC International Division

Kott Group

Cold Climate Social Housing - a case study

Page 2: Sdrhcon2011 armstrong

• 2 million km2

• 26 communities

• 30,000 people

• Iqaluit - pop: 7,000

• No roads

Page 3: Sdrhcon2011 armstrong

• 2 million km2

• 26 communities

• 30,000 people

• Iqaluit - pop: 7,000

• No roads

Approximately 8,500 dwellings

80% are public, gov’t staff or rent subsidized housing

Nearly half of all houses are below Canadian housing standards

Current shortfall of 3,000 units

Average annual new-build - 200 units

Funding committed for 2012 - 2013 - $0.00

The scale of the housing problem...

Page 4: Sdrhcon2011 armstrong

Average house size - 93 sq. m.

Median number of people in a home is 6

Half of Nunavut’s homes are overcrowded or need serious repair.

4% of the population does not have a permanent home and bounce between homes often sleeping in shifts on couches, in kitchens, dining rooms or hallways

Tuberculosis rate 62 times the Canadian average

Highest birth rate & lowest life expectancy in Canada

Health and social impacts...

Page 5: Sdrhcon2011 armstrong

“There is a strong correlation between the state of housing in Nunavut and domestic violence, mental health problems, substance abuse, poor academic performance, respiratory ailments and the spread of infectious diseases”

Nunavut 10 year Inuit Housing Action Plan

".…the conditions in far too many Aboriginal communities can only be described as shameful. This offends our values. It is in our collective interest to turn the corner. And we must start now."

The Right Honourable Adrienne Clarkson - Speech from the Throne, February 2, 2004

The bottom line...

Page 6: Sdrhcon2011 armstrong

The Challenge

To provide a high performance building enclosure system that is easy to put up quickly in Northern conditions at a reasonable cost.

Page 7: Sdrhcon2011 armstrong

Nunavut Housing Corporation RFP - June 2009

Page 8: Sdrhcon2011 armstrong

Nunavut Housing Corporation RFP - June 2009

StructureThermal ControlVapour ControlAir Leakage Control

Page 9: Sdrhcon2011 armstrong

Nunavut Housing Corporation RFP - June 2009

StructureThermal ControlVapour ControlAir Leakage Control

Page 10: Sdrhcon2011 armstrong

Plywood skins

R - 50 Floor, R - 40 Walls, R - 50 Roof

Air leakage control without caulking or spray foam - 0.5 AC/h @ 50 Pa

Nunavut Housing Corporation RFP - June 2009

Structural insulated panels

Page 11: Sdrhcon2011 armstrong

Blower Door Testing

R-2000 - 1.5 ac/h@ 50 Pa

PassivHaus - 0.6

Nunavut Housing - 0.5

Page 12: Sdrhcon2011 armstrong

Plywood skins

R-50 Floor, R-40 Walls, R-50 Roof

Air leakage control without caulking or spray foam - 0.5 AC/h @ 50 Pa

Capable of being handled by hand or machine

Designed to meet highest wind and snow loads in Nunavut

“Closed Cell” foam (vapour control)

Thick enough to incorporate structural elements

Nunavut Housing Corporation RFP - June 2009

Structural insulated panels

Page 13: Sdrhcon2011 armstrong

Project TimelineReceived RFP - June 26 / 09

Tender closed in Iqaluit - July 17

Tender Award - August 6

D1 erected at Kott Yard - September 14 - 18

D1 erected in Morrisburg - September 21 - 26

Authorization to Proceed - October 30

D2 erected at Kott Yard - December 9 - January 10

Production Starts - January 4

Crates to Port - April 3 - July 15

Total Production: 15,336 panels; 1,420 crates

Page 14: Sdrhcon2011 armstrong
Page 15: Sdrhcon2011 armstrong

5 24 3 16

C B A

1 BUILDING SECTION 2 BUILDING SECTION

ASSEMBLY SCHEDULE3

ROOM FINISH SCHEDULE4

A4

BUILDING SECTIONS,ASSEMBLY &

FINISH SCHEDULES

PH. (867) 6690058

P.O. BOX 1525YELLOWKNIFE, N.W.T.

FAX.(778) 2850033

email: [email protected] site: tjtechnical.ca

X1A 2P2

08220

3 BEDROOM SINGLEFAMILY DWELLING

AMARUK

Grade Insulated floorCrawlspace

Page 16: Sdrhcon2011 armstrong

5 24 3 16

C B A

1 BUILDING SECTION 2 BUILDING SECTION

ASSEMBLY SCHEDULE3

ROOM FINISH SCHEDULE4

A4

BUILDING SECTIONS,ASSEMBLY &

FINISH SCHEDULES

PH. (867) 6690058

P.O. BOX 1525YELLOWKNIFE, N.W.T.

FAX.(778) 2850033

email: [email protected] site: tjtechnical.ca

X1A 2P2

08220

3 BEDROOM SINGLEFAMILY DWELLING

AMARUK

Grade Insulated floorCrawlspace

Page 17: Sdrhcon2011 armstrong

CONSTRUCTIONNORTH

A

B

C

2 653 41

CONSTRUCTIONNORTH

61

A1 A1

2 53 4

A2

FLOOR PLANSPH. (867) 6690058

P.O. BOX 1525YELLOWKNIFE, N.W.T.

FAX.(778) 2850033

email: [email protected]

T.J. TECHNICAL SERVICES

web site: tjtechnical.ca

X1A 2P2

08220

3 BEDROOM SINGLEFAMILY DWELLING

AMARUK

Page 18: Sdrhcon2011 armstrong

Solution

R-40 Walls (12”)R-50 Floor (14-5/8”)R-50 Roof (14-5/8”)

Page 19: Sdrhcon2011 armstrong

Critical month ACH (Natural) 4.43 0.50Critical month ACH (Total) 0.486 0.256

ANNUAL FUEL CONSUMPTION SUMMARYOil (Imp. Gal) 810.6 387.5Electricity (Mil. Btu) 8767.4 9092.5

ESTIMATED FUEL COSTS (Dollars)Oil 1614.4 834.3Electricity 909.5 941.2

Total 2523.9 1775.4ANNUAL SPACE HEATING SYSTEM PERFORMANCESpace Heating Load (Mil.BTU) 93.8 34.1Furnace Input (Mil.BTU) 111.0 40.7Pilot Light (Mil.BTU) 0.0 0.0Indoor Fans (Mil.BTU) 0.0 0.0Heat Pump Input (Mil.BTU) 0.0 0.0Total Input (Mil.BTU) 111.0 40.7System COP 9.8 7.5

Hot 2000 Version 10.31 C:\DOCUME~1\ADMINI~1... 29/10/2009 - 4:46:57 PM

Page 2 of 2

HOUSE DATACOMPARISON REPORT

HOT2000Natural Resources CANADA

Version 10.31

Nunavut-MNECCH Nunavut-SIP

AIR LEAKAGE AND VENTILATION SYSTEMSHouse Volume (ft3) 15931.0 15931.0

Envelope Surface Area (ft2) 3949.9 3949.9Natural Infiltration Rate (ACH) 0.285 0.032

Equivalent Leakage Area (in2) 115.7 13.1Central Ventilation Supply Rate (ACH) 0.040 0.270Central Ventilation Exhaust Rate (ACH) 0.040 0.270Other Supply Rate (ACH) 0.000 0.000Other Exhaust Rate (ACH) 0.000 0.000Seasonal HRV Efficiency (%) 59.0 57.7Gross Air and Vent. Energy (Mil.BTU) 44.5 32.1Vent. Elec. Load: Heating Hrs (Mil.BTU) 0.0 1.1Vent. Elec. Load: Non Htg Hrs (Mil.BTU) 0.0 0.0Net Air and Vent. Energy (Mil.BTU) 44.3 16.3

ANNUAL SPACE HEATING SUMMARYDesign Heat Loss (Watts) 39523 22648Gross Space Heat Loss (Mil.BTU) 129.5 63.3Sensible Occupancy Heat Gain (Mil. Btu/day) 2.40 2.40Usable Internal Gains (Mil.BTU) 27.0 24.8Usable Internal Gains Fraction (%) 20.9 39.1Usable Solar Gains (Mil.BTU) 8.7 4.4Usable Solar Gains Fraction (%) 6.7 7.0Vent. Electrical Contribution (Mil.BTU) 44.3 16.3Auxiliary Energy Required (Mil.BTU) 93.8 34.1SPACE + DHW ENERGY (Mil.BTU) 134.6 65.5R-2000 SPACE + DHW TARGET (Mil.BTU) 110.2 110.2

ENERGUIDE RATING (0 to 100) 76.2 86.1Air Change Rate at 50 Pa. 76.2 86.1

Hot 2000 Version 10.31 C:\DOCUME~1\ADMINI~1... 29/10/2009 - 4:46:57 PM

Page 1 of 2

HOUSE DATACOMPARISON REPORT

HOT2000Natural Resources CANADA

Version 10.31

Nunavut-MNECCH Nunavut-SIP

AIR LEAKAGE AND VENTILATION SYSTEMSHouse Volume (ft3) 15931.0 15931.0

Envelope Surface Area (ft2) 3949.9 3949.9Natural Infiltration Rate (ACH) 0.285 0.032

Equivalent Leakage Area (in2) 115.7 13.1Central Ventilation Supply Rate (ACH) 0.040 0.270Central Ventilation Exhaust Rate (ACH) 0.040 0.270Other Supply Rate (ACH) 0.000 0.000Other Exhaust Rate (ACH) 0.000 0.000Seasonal HRV Efficiency (%) 59.0 57.7Gross Air and Vent. Energy (Mil.BTU) 44.5 32.1Vent. Elec. Load: Heating Hrs (Mil.BTU) 0.0 1.1Vent. Elec. Load: Non Htg Hrs (Mil.BTU) 0.0 0.0Net Air and Vent. Energy (Mil.BTU) 44.3 16.3

ANNUAL SPACE HEATING SUMMARYDesign Heat Loss (Watts) 39523 22648Gross Space Heat Loss (Mil.BTU) 129.5 63.3Sensible Occupancy Heat Gain (Mil. Btu/day) 2.40 2.40Usable Internal Gains (Mil.BTU) 27.0 24.8Usable Internal Gains Fraction (%) 20.9 39.1Usable Solar Gains (Mil.BTU) 8.7 4.4Usable Solar Gains Fraction (%) 6.7 7.0Vent. Electrical Contribution (Mil.BTU) 44.3 16.3Auxiliary Energy Required (Mil.BTU) 93.8 34.1SPACE + DHW ENERGY (Mil.BTU) 134.6 65.5R-2000 SPACE + DHW TARGET (Mil.BTU) 110.2 110.2

ENERGUIDE RATING (0 to 100) 76.2 86.1Air Change Rate at 50 Pa. 76.2 86.1

Hot 2000 Version 10.31 C:\DOCUME~1\ADMINI~1... 29/10/2009 - 4:46:57 PM

Page 1 of 2

H2K Modeling - Bruce Gough, Energy Building GroupSolution

Critical month ACH (Natural) 4.43 0.50Critical month ACH (Total) 0.486 0.256

ANNUAL FUEL CONSUMPTION SUMMARYOil (Imp. Gal) 810.6 387.5Electricity (Mil. Btu) 8767.4 9092.5

ESTIMATED FUEL COSTS (Dollars)Oil 1614.4 834.3Electricity 909.5 941.2

Total 2523.9 1775.4ANNUAL SPACE HEATING SYSTEM PERFORMANCESpace Heating Load (Mil.BTU) 93.8 34.1Furnace Input (Mil.BTU) 111.0 40.7Pilot Light (Mil.BTU) 0.0 0.0Indoor Fans (Mil.BTU) 0.0 0.0Heat Pump Input (Mil.BTU) 0.0 0.0Total Input (Mil.BTU) 111.0 40.7System COP 9.8 7.5

Hot 2000 Version 10.31 C:\DOCUME~1\ADMINI~1... 29/10/2009 - 4:46:57 PM

Page 2 of 2

MNEC

Page 20: Sdrhcon2011 armstrong

SolutionExpanded Polystyrene core with plywood skins

Skins glued to core with urethane to provide vapour control

Peel & stick on panel joints for air leakage control

Nascor i-joist splines

All panels thermally broken

Page 21: Sdrhcon2011 armstrong

SolutionExpanded Polystyrene core with plywood skins

Skins glued to core with urethane to provide vapour control

Peel & stick on panel joints for air leakage control

Nascor i-joist splines

All panels thermally broken

Soft foam gaskets at panel joints

Page 22: Sdrhcon2011 armstrong

SolutionExpanded Polystyrene core with plywood skins

Skins glued to core with urethane to provide vapour control

Peel & stick on panel joints for air leakage control

Nascor i-joist splines

All panels thermally broken

Soft foam gaskets at panel joints

Construction Guide & Training DVD - with Inuktitut Translation

Page 23: Sdrhcon2011 armstrong

D1 Morrisburg

Page 24: Sdrhcon2011 armstrong

D1 Morrisburg

Page 25: Sdrhcon2011 armstrong

D1 Morrisburg

Page 26: Sdrhcon2011 armstrong

D1 Results

Floor complete in 3.5 hrs. - 5 man crew

Complete shell of house erected and tested for air leakage in 4.5 days

Page 27: Sdrhcon2011 armstrong

D2 Kott Yard

Page 28: Sdrhcon2011 armstrong

D2 Blower Door Results

R-2000 - 1.5 AC/h @ 50 Pa

Client Spec - 0.5

D1 - 0.67

D2 - #1 - 0.21

D2 - #2 - 0.19

Page 29: Sdrhcon2011 armstrong

Training Team

Page 30: Sdrhcon2011 armstrong

29 units

113 units

Page 31: Sdrhcon2011 armstrong
Page 32: Sdrhcon2011 armstrong
Page 33: Sdrhcon2011 armstrong
Page 34: Sdrhcon2011 armstrong

On-site construction started August 15 - 2010

115 house shells erected by December 20 - 2010

Page 35: Sdrhcon2011 armstrong

Pangnirtung - Nov. 27, 2010

Page 36: Sdrhcon2011 armstrong
Page 37: Sdrhcon2011 armstrong
Page 38: Sdrhcon2011 armstrong

Loading...

©2011 Google - Map data ©2011 Europa Technologies, Google -

We could not calculate directions between Iqaluit, NU and Igloolik, NU.

Iqaluit, NU to Igloolik, NU - Google Maps http://maps.google.ca/maps?f=d&source=s_d&saddr=Iqaluit,+...

1 of 1 11-01-26 2:46 PM

BaffinIsland

HudsonBay

IqaluitCoral

Harbor

Arviat

RankinInlet

RepulseBay

Igloolik

December 14 & 15 2010

Page 39: Sdrhcon2011 armstrong

December 14 & 15 2010

Page 40: Sdrhcon2011 armstrong

Field Notes:21 houses inspected

Working Conditions - minus 40 deg. C / dark

Some foundations off level

Some walls installed off plumb

Some panels not pulled completely together

Page 41: Sdrhcon2011 armstrong
Page 42: Sdrhcon2011 armstrong

Field Notes:

Air leakage control much better than required

21 houses inspected

Working Conditions - minus 40 deg. C / dark

Some foundations off level

Some walls installed off plumb

Some panels not pulled completely together

Thermal imaging indicates open joints still perform well

Page 43: Sdrhcon2011 armstrong

What about costs?Slightly more than stick-built

Unfamiliarity with SIPs = higher labour pricing

Underutilized local labour

Buildings will be monitored to confirm heating cost savings

Turnkey = lower price

System refinements & manufacturing efficiencies = lower price

Page 44: Sdrhcon2011 armstrong

Multi-unit Arctic SIP houses