67
Longitudinal Joints in Asphalt Pavements 37 th Annual Utah Asphalt Conference March 27, 2012 Howard Anderson, PE. UDOT Central Materials

Long Joint Presentation -- Short Version

Embed Size (px)

DESCRIPTION

 

Citation preview

Page 1: Long Joint Presentation -- Short Version

Longitudinal Joints in Asphalt Pavements

37th Annual Utah Asphalt ConferenceMarch 27, 2012

Howard Anderson, PE.

UDOT Central Materials

Page 2: Long Joint Presentation -- Short Version

Acknowledgements

• FHWA and Asphalt Institute Partner to Identity Best Practices for Longitudinal Joints. Training Class, February 23, 2012. Mark Buncher, Ph.D., P.E.

• NCAT Report No. 97-4 Longitudinal Joint Construction Techniques for Asphalt Pavements.

Page 3: Long Joint Presentation -- Short Version

Best Practices forSpecifying and Constructing

HMA Longitudinal Joints

A Cooperative Effort betweenAsphalt Institute & FHWA

Page 4: Long Joint Presentation -- Short Version

Definitions

• Longitudinal Joint – HMA placed adjacent to existing lane, Interface between two existing HMA mats.

• Hot Joint – Adjacent lanes paved in echelon.

• Cold Joint – first pass cooled to ambient temperature with next HMA pass.

Page 5: Long Joint Presentation -- Short Version

Longitudinal Joint

Performance equals

Mat Performance

Goal LJP = MP

Page 6: Long Joint Presentation -- Short Version

Is It a Problem?

Page 7: Long Joint Presentation -- Short Version

LCC Alternate Bid Competitiveness DOT Program Costs HMA Industry’s Livelihood the Travelling Public

An Agency and Industry Concern

Longevity matters, it impacts:

Page 8: Long Joint Presentation -- Short Version

Project Team– Asphalt Institute

• Mark Buncher• Carlos Rosenberger• AI Regional Engineers

– FHWA• Thomas Harman• Michael Arasteh• Stephen Cooper

– PA State Asphalt Paving Association• Gary Hoffman

National Asphalt Pavement Association• David Newcomb

Page 9: Long Joint Presentation -- Short Version

How many State Agencies have a longitudinal joint specification?

•About thirdA

•About halfB

•About two-thirdsC

Page 10: Long Joint Presentation -- Short Version

Takeaways from FHWA Survey to 52 Division Offices

• ½ States are not satisfied with overall performance of L-Joints

• 2/3rds of States have a “L-Joint spec”– Half of those (17) require a minimum density

• Range from 89% - 92% min Gmm (Rice)

– Other half are method specs• From Joint Adhesive to very prescriptive

Page 11: Long Joint Presentation -- Short Version

312

Trucking Compaction

Paving Plant

Dump Person MTV

GETTING STARTED OFF RIGHT

Page 12: Long Joint Presentation -- Short Version

Managing Material in the Hopper

Conveyor area is exposed and augers are starved!

Page 13: Long Joint Presentation -- Short Version

Tack Coat

Full width of mat to minimize movement of unsupported edge

Page 14: Long Joint Presentation -- Short Version

Dump Person

Page 15: Long Joint Presentation -- Short Version

First Pass Must Be Straight!Unanimous that a string-line should be used to assure first

pass is straight

String-line Skip Paint Reference

Page 16: Long Joint Presentation -- Short Version

Great Results

Page 17: Long Joint Presentation -- Short Version

Paver operator using the curb as his reference

Page 18: Long Joint Presentation -- Short Version

Tough to get proper overlap (1”) with next pass

Page 19: Long Joint Presentation -- Short Version

Contact Grade Sensor

Ultrasonic Grade Sensor

Use Automatic Control

Systems

Page 20: Long Joint Presentation -- Short Version

Vibratory Screed Should Always Be On

Page 21: Long Joint Presentation -- Short Version

Department, Name, Security Class 23Date

Forward Motion

Screed Weight

Screed HeatingVibration

Angle of Attack

Achieving Pre-Compaction

Page 22: Long Joint Presentation -- Short Version

END GATE

Seated on the Existing Surface

Page 23: Long Joint Presentation -- Short Version

Uniform Head of MaterialAcross the Entire Screed

Auger

Carry Material Within12 – 18-inches of

the End Gate

Page 24: Long Joint Presentation -- Short Version

Another example of uniform head of material

Page 25: Long Joint Presentation -- Short Version

Controlling material flow at outer edges of screed and

delivering homogenous HMA

Hydraulic Extending Tunnels

Tunnels

Page 26: Long Joint Presentation -- Short Version

Result of uniform head of HMA and auger/tunnel within 12 to 18-inches of end gate: non-segregated HMA at the joint

Page 27: Long Joint Presentation -- Short Version

Auger Overload…these are unacceptable

Page 28: Long Joint Presentation -- Short Version

Auger not extended towithin 12 to 18-inches of the end gate.

The result -SEGREGATION at joint

Page 29: Long Joint Presentation -- Short Version

Rollers Need to Be Kept Close to the PaverCritical in cool and cold weather!

Page 30: Long Joint Presentation -- Short Version

Our Recommendation:1st Roller Pass Hangs Over 4-6 inches

Page 31: Long Joint Presentation -- Short Version

Alternative: Stay Back 4-6 inches on 1st pass, then roll 2nd pass w/

slight overhang

• Concern:–developing

stress crack?

• Merit:–minimize

lateral movement?

Page 32: Long Joint Presentation -- Short Version

What We Don’t Want

Edge of drum inside unsupported edge

can cause cracking near the edge

Rolling Unsupported Edge

(First Paver Pass)

Page 33: Long Joint Presentation -- Short Version

Compacting Notched Wedge

add-on vibratory compactorplate compactor

Page 34: Long Joint Presentation -- Short Version

Quality Control, Monitor Joint Density

Page 35: Long Joint Presentation -- Short Version

Tack the Joint! (Butt or Wedge)

Emulsion, or

PG asphalt or Proprietary Joint Adhesive (JA)

Good, Better, Best

Page 36: Long Joint Presentation -- Short Version

Paver Automation Using Joint Matcher (versus Ski) to Always Achieve Exact

Thickness of Mat Needed

If the joint (hot-side) is starved of material, the roller drum will “bridge” onto the cold mat and no further density will occur at joint. To ensure this never occurs, target height difference after compaction is 0.1”

Page 37: Long Joint Presentation -- Short Version

Destined for Failure Hot side of joint

starved of material.Bridging?

Page 38: Long Joint Presentation -- Short Version

Types of Joint Matchers

G. Bridenbaugh photo

Frank Colella photo

Non-contact sensor

Contact sensor

Page 39: Long Joint Presentation -- Short Version

Ski best for smoothness

Arm

Averages optimum HMA thickness over entire length of ski.

Page 40: Long Joint Presentation -- Short Version

Proper Overlap: 1.0 + 0.5 inches.

Exception: Milled or sawed joint should be 0.5 inches

Page 41: Long Joint Presentation -- Short Version

Bridenbaugh & Colella

Top Photos Show Voids at Bottom of Lift (no overlap)

Page 42: Long Joint Presentation -- Short Version

Bumping the joint?

Page 43: Long Joint Presentation -- Short Version

Don’t broadcast material across the mat

Page 44: Long Joint Presentation -- Short Version

Lute the Longitudinal Joint

This lute person isdoing a great job

Page 45: Long Joint Presentation -- Short Version

No lute person

Page 46: Long Joint Presentation -- Short Version

1st pass off the jointapprox 6-8 inches

2nd pass overlap onto the cold mat

Rolling the Supported Edge

Our Recommendation:

Page 47: Long Joint Presentation -- Short Version

Roller

Make a roller pass in the vibratory mode overhanging 2 to 4-inches on the cold side.

versus an Alternate Method of1st Pass over the Supported Edge

Concern is bridging (roller being supported by cold mat)

Page 48: Long Joint Presentation -- Short Version

• Plant tons/hour• # of trucks• Plant to project (time)• Type of project

(rural/urban)• Ambient / Surface temps• Paver speed• # of rollers

On this day goal was 35 ft/min

Contractor Prior Planning

Consideration given to mix selection

Plan joint offsets when multiple lifts

Page 49: Long Joint Presentation -- Short Version

Tack Full Width to Minimize Lateral Movement

Page 50: Long Joint Presentation -- Short Version

Paver on Automatic

Page 51: Long Joint Presentation -- Short Version

Vibratory Screed “ON”

Page 52: Long Joint Presentation -- Short Version

End Gate Tight to the Existing Surface

Page 53: Long Joint Presentation -- Short Version

First Pass Must be Straight

Page 54: Long Joint Presentation -- Short Version

Uniform head of materialacross entire screed to joint…Do Not Overload Auger

Extend auger and tunnel within 12 to 18-inches of the end gate

Page 55: Long Joint Presentation -- Short Version

Rolling Unsupported Edge: Overlap 6-inches on the First Pass

Page 56: Long Joint Presentation -- Short Version

Tack / Paint the Vertical Face

1. Joint Adhesive2. PG Binder3. Double Tack

with Emulsion

Page 57: Long Joint Presentation -- Short Version

Overlap the cold lane by 1-inch +/-(unless milled or cutback joint, then 0.5-inch) Use a Joint Matcher

Page 58: Long Joint Presentation -- Short Version

Do Not Push Overlap Back

Page 59: Long Joint Presentation -- Short Version

Rolling Supported Edge: Stay off the Joint 6 to 12 inches on the first pass

Page 60: Long Joint Presentation -- Short Version

Making sure everythingis just right

Attention to Detail

Monitor density with gauge, on both sides of the joint, as part of QC program

Page 61: Long Joint Presentation -- Short Version

Less permeable mixes• Smallest NMAS that will do the job• Consider using a “fine” gradation• Lower gyration levels

Min lift thickness is NMAS x 4, exception: for “fine” gradation NMAS x 3 Warm Mix Asphalt may serve as compaction aid Pay for tack as a separate bid item to facilitate proper

application rate

Consider use of the notch wedge joint (versus butt) for lift thicknesses > 1.5 inches and < 3 inches

Mix Selection and Design Considerations

Page 62: Long Joint Presentation -- Short Version

Offset longitudinal joints between layers by at least 6-inches

Page 63: Long Joint Presentation -- Short Version

Innovative Techniques / Materials

• Infrared Joint Heaters– In cold weather

• Evaluate Project and Traffic Control Requirements for:– Echelon Paving– Mill / Fill One Lane at a Time– Cutting Back the Joint

• Consider Joint Enrichment – Overbanding with PG Binder – Use of Surface Sealers

Page 64: Long Joint Presentation -- Short Version

I-68 project 5+ years old

GOAL

Page 65: Long Joint Presentation -- Short Version

I-68 project 5+ years old

( same project, same location as previous slide )

Page 66: Long Joint Presentation -- Short Version

Industry Help Needed HMA

• Concrete getting more competitive due to HMA cost increase.

• Concrete has worked out many of its problems with smoothness.

• HMA problems with Longitudinal Joints, durability, dry mixes.

• UAPA can bring one voice to UDOT to represent best interest of the industry, not just one contractor.

Page 67: Long Joint Presentation -- Short Version

We Know Unsupported Edge Will Have Lower Density

Proper Overlap Sufficient Materialfor Roll-Down

Low Density Area