37
CHAPTER 4 : TECHNICAL REPORT VARIATION ORDER 4.1 Introduction Variation Order (VO) is meant any additions, replacement, omission or changes to the specifications, drawings or quantity on a contract or original work. Any Variation (VO) can only be performed by the contractor in the event of a formal directive issued by the Superintending Officer (SO). - Variation to the original work is almost certain to happen in construction projects due to : 29

Laporan Latihan Industri Bab 4

Embed Size (px)

DESCRIPTION

#POLITEKNIK #UKUR BAHAN #LAPORAN # REPORT #LATIHAN #INDUSTRI

Citation preview

Page 1: Laporan Latihan Industri Bab 4

CHAPTER 4 : TECHNICAL REPORT

VARIATION ORDER

4.1 Introduction

Variation Order (VO) is meant any additions, replacement, omission or

changes to the specifications, drawings or quantity on a contract or original

work. Any Variation (VO) can only be performed by the contractor in the

event of a formal directive issued by the Superintending Officer (SO).

- Variation to the original work is almost certain to happen in construction

projects due to :

a) Site conditions.

b) Statutory requirements.

c) Change in client’s requirements.

29

Page 2: Laporan Latihan Industri Bab 4

d) Defective contract drawings, bills of quantities, specification, etc.

(including intentional abuse of variation clause since contract

allows changes to design, etc.)

e) Poor cost control e.g. omissions required due to shortage of fund.

- Most forms of contract have provisions which will allow any necessary

changes to be made during the construction process.

- Without the variation clause, changes to the original contract are not

allowed. If changes to the works are necessary :

a) Separate contract has to be drawn up (e.g. for additional work)

b) A new contract has to be prepared to replace the existing contract

(e.g. changes in design)

- For contract based on bills of quantities – the contractor has the right to

claim under variation for carrying out the works not provided for or

measured in the bill of quantities.

- For contract based on drawings and specifications – the contractor does

not have the right to claim under variation for carrying out all works

incidental or necessary for the completion of the work even though those

works are shown in the drawings and described in the specifications.

30

Page 3: Laporan Latihan Industri Bab 4

4.2 P.W.D Form 203A (Rev. 2007)

- The relevant contractual provisions regarding variations are as shown in

Table 4.2.1.

P.W.D Form 203A (Rev. 2007)

Clause 5.0 – S.O Instructions

Clause 24.0 – Variations

Clause 25.0 – Valuation of variation

Clause 34.0 – P.C and Provisional sums

Clause 28. 0 – Payment to contractor and Interim certificates

Table 4.2.1 – Contractual Provisions Regarding Variations.

- The above clauses explain the procedure to be adhered to in the variation

process which include :

a) The power to order variations.

b) The methods of valuations for variations.

c) the amount to be paid to the contractor.

d) The procedure and conditions precedent.

31

Page 4: Laporan Latihan Industri Bab 4

4.3 Variations

‘The term alteration means a change in the Contract Document which

necessitates the alternation or modification of the design, quality or

quantity of the works…and affects the Contract Sum, including :

a) The addition , omission or substitution of any work.

b) The alteration of the kind or standard of any materials, goods to

be used in the works, or

c) The removal from the site of any work executed or materials or

goods brought thereon by the Contractor for the purposes of

the Works…’ (Clause24,2)

Figure 4.3.1 – Type of Variations of Work

32

Variations

Removal of materials brought onto site

Change of quantity of work

Change of quality of workRemoval of work

executed on site

Change of design of work

Page 5: Laporan Latihan Industri Bab 4

- A variation means any change to the work as described in the contract

document i.e. as shown in the drawings , described in the Specification,

Bills of quantities, etc.

- A variation includes :

a) The change to the works/materials

i. The change of quality of the work.

- increase or decrease the quality of any work included in the

contract i.e. change of specification level of the work.

ii. The change of quantity of the work.

- Increase or decrease the quantity of any work included in

the contract.

iii. The change of design of the work.

- Omit any work included in the contract.

- Carry out additional work originally not included in the

contract.

- Substitute any work in the contract.

- Change the level , positions , dimensions of any work in the

contract.

- Change the kind of materials to be used in the work.

- Change the shape and colour of the works.

33

Page 6: Laporan Latihan Industri Bab 4

b) The removal of materials brought onto site. The materials removed

must be intended or required for the work.

i. The removal of materials not in accordance with the contract is

not a variation. The S.O.’s instruction is given according to

Clause 5.1 (c)

c) The removal of works executed on site. The works removed must

have been done according to the contract.

i. The removal of works not in accordance with the contract is not

a variation. The S.O.’s instruction is given according to Clause

5.1 (c)

34

Page 7: Laporan Latihan Industri Bab 4

4.4 Procedure of Variations

Figure 4.4.1 – Variations Process

35

S.O. issues instruction to contractor (Clause 24.1)

CONTRACTOR carries out the work (Clause 24.1)

S.O. measures, values the certifies work (Clause 25.1, 25.3)

EMPLOYER pays contractor through interim payment (Clause 28.6)

Page 8: Laporan Latihan Industri Bab 4

4.5 Instructions for Variations

4.5.1 Power to Issue Instruction

‘The S.O. may from time to time issue further drawings, details and/or

written instructions (All of which are hereafter collectively referred to as

“S.O.’s instructions”) in regard to : (a) The Variation..’ (Clause 5.1)

- The S.O. has the power to issue instructions to cover not only variations

but many other areas for proper execution of the work.

- Not every instruction constitutes a variation but every variation requires

an instruction. The contractor therefore cannot expect payment for every

work that he did in compliance with the instruction.

- The contractor may request the S.O. to specify the contract condition

which empowers him to issue instruction.

- Instruction given by any other person will not valid.

‘…No variation required by the S.O shall vitiate this Contract...’

(Clause 24.1)

- The S.O. has full power to issue instructions to the contractor to carry out

any variation work which he thinks necessary for satisfactory completion

of the project.

- Generally, any variation instructed by the S.O. is allowed under the

contract and it will not be in breach of contract.

36

Page 9: Laporan Latihan Industri Bab 4

- However changing the original scope of work is not allowed. The variation

should not fall outside the scope of works contemplated by the parties at

the time when the contract was made. The contract does not authorize

extra work not related to the original project.

- Omission of work is allowed under the contract (Sub-clause 25(b)(iii)).

The limitations are as follows :

a) Invalid omission – the S.O. may omit work only if it is not to be

done at all. The omitted work cannot be carried out by another

person. Galagher v. Hirsh (1899) – work was omitted and given to

another contractor was held to be a breach of contract.

b) Substantial omission – extensive omission that substantially

changes the character of the work will be a ground for claim for

breach of contract by the contractor.

4.5.2 Written Instructions

‘All instructions issued by the S.O. shall be in writing. The Contractor

shall forthwith comply with all instructions issued to him by the S.O. If

such instruction is given orally, the S.O. shall then issue a written

instruction within seven (7) days from the date of such oral instruction

is given.’ (Clause 5.2).

- An oral instruction is of no immediate effect and it does not bind the

contractor to comply with it.

37

Page 10: Laporan Latihan Industri Bab 4

Oral instruction Confirmation in writing

≤ 7 Days

Figure 4.5.2.1 – Comfirmation of Oral Instruction.

- Any oral instruction must be comfirmed later in writing within 7 days after

its issuance by the S.O. himself. The instruction only takes effect upon

confirmation.

- The contractor will have to bear the cost of complying to the oral

instruction if the S.O. does not confirm the oral instruction within 7 days –

the S.O. is not bound to do so.

‘The S.O. may issue instructions requiring a Veration in a form of a

Variation Order..’ (Clause 24.1).

- All instruction regarding variations issued by the S.O. must be in writing

and in a recognized format entitled Variation Order as shown in Figure

4.5.1.1.

- The particulars to be stated by the S.O. in the Variation order include :

a) Description of variation.

b) Estimated cost of variation.

c) Cumulative total value of variations to date.

38

Page 11: Laporan Latihan Industri Bab 4

Non – compliance Non – compliance7 Days

S.O.’s InstructionNotice requiring contractor to comply with instruction

S.O.’s decisions : -do the work departmentally -employ another contractor

4.5.3 Compliance to Instructions

‘..Upon the issuance of such Variation Order, the Contractor shall

forthwith comply with the Variation Order issued by the S.O.’ (Clause

24.1)

‘If within seven (7) days after receipt of the written notice from the S.O.

requiring compliance to an instruction and the Contractor does not

comply therewith, then the S.O. …undertake the work departmentally,

or employ and pay another contractor or any other persons to execute

any work…’ (Clause 5.3)

- The contractor must comply with the S.O.’s instruction immediately.

- If the contractor does not comply with the instruction, the S.O. will send a

notice to the contractor requiring the contractor to comply with the

instruction.

Figure 4.5.3.1 – Non-compliance to Instruction by Contractor.

- If the contractor still does not comply with the instruction within 7 days

after receiving the notice, the S.O. may take the following actions :

a) Execute the work departmentally.

b) Engage another contractor to carry out the work

39

Page 12: Laporan Latihan Industri Bab 4

‘…. All cost and expenses incurred in connection with such

employment (including On-Cost Charges), shall be deducted from any

money due or to become due to the Contractor under this Contract,

and failing which such deduction shall be recovered from the

Performance Bond or as a debt due from the Contractor..’ (Clause 5.3)

- The payment made to the third party or the employer himself for

executing the work can be deducted from the contract sum, performance

guarantee sum, etc.

- The employer can also claim for on-cost charges – the cost and expenses

incurred by the employer in getting the work done by another contractor

or by the employer himself.

- The percentage for on-cost charges is fixed in the Appendix as 5% of the

cost of the affected work.

- If the contractor carries out the work that is outside the work he was

bound to do for original contract price without S.O.’s instruction :

a) the contractor will not be paid for the work.

b) the contractor is in breach of contract for not carrying out the work

according to the contract – he may have to remove the work and

replace it with the work according to the contract.

40

Page 13: Laporan Latihan Industri Bab 4

- In the case of differences between actual quantities and the quantities

stated in the bills of quantities :

a) No instruction is required.

b) The contractor is bound to carry out works in excess of those

stated in the bills of quantities.

41

Page 14: Laporan Latihan Industri Bab 4

4.6 Measurement of variations

4.6.1 Generally

‘All variations instructed in writing… shall be measured and valued by

the S.O….’ (Clause 25.1)

- The S.O. is responsible to measure and value the variation works done by

the contractor.

- The measurement and valuation of the works should be done as soon as

possible to enable payment for the works to be included in the interim

payment certificates.

- The variation work which is to be treated as the work done by the

contractor has to be paid in the interim payment certificates even though

Certificate Of Adjustment Of Contract Sum is not yet prepared.

- The S.O. is only required to measure variations that have been confirmed

in writing.

- Method: Omit the work from the contract bills and add the measurement

of the work carried out as instructed.

‘The S.O. … the works to be measured … give reasonable notice to

the Contractor who shall attend or send a qualified agent to assist the

S.O. … shall furnish all particulars required by the S.O.. Should the

Contractor fail to attend… the measurement made by the S.O. or

approved by him shall be taken the correct measurement of the work’.

(Clause 27.1)

42

Page 15: Laporan Latihan Industri Bab 4

- The measurement of work will used for the valuation of variation.

- The measurement sometimes needs to be done on site especially when

the measurement cannot be accurately done based on the available

information or drawings.

- The S.O should carry out measurement of the variation work jointly with

the contractor.

- The S.O. will send a notice to the contractor informing him about the

measurement to be made.

- The contractor is required to take part in the measurement even though

the contractor does not participate in the measurement after being told to

do so.

43

Page 16: Laporan Latihan Industri Bab 4

4.7 Valuation of variations

4.7.1 Generally

‘… The valuation of Variations, unless previously or otherwise

agreed, shall be made in accordance with the following rules :’

(Clause 25.1)

- The S.O has to make the valuation of the varied work in order to arrive at

the amount to be paid to the contractor.

- The provision lists down the rates or prices to be used in the valuation of

the works.

4.7.2 Contract Rates

‘the rates in the Bills of Quantities… shall determine the valuation of

work of similar character and executed under similar conditions as

work priced therein.’ (Clause 25.1 (a)).

‘the rates in the Bills of Quantities shall determine the valuation of

items omitted, …’ (Clause 25.1(c)).

- These contract or B.Q. rates are applicable for valuing:

a) Similar work i.e. varied works which are of similar character and

executed under similar conditions to the work in the Bills of

quantities.

b) Omitted work.

44

Page 17: Laporan Latihan Industri Bab 4

- The rates are taken from the bills of quantities. Reference to the bills of

quantities should be made when these rates are used in the valuation of

varied works.

- Percentage adjustment is required to be made on the contract rates if

necessary.

Example 1 : Application of B.Q. rate.

VO Title :

VO Detail :

Employer's Representative Instruction closed out : IDMS/MED/INFRA 3/2011/EI-____

Element Unit RM RateOmission Addition

SOW NO. 12- PPU (44,382.90) 54,007.50

(44,382.90) 27,042.60

(88,765.80) 81,050.10

(7,715.70)

Total

Nett Omission :-

Additional perimeter drain and brick sump at PPU No. 3 and PPU No. 4.

RM Value Description

Additional perimeter drain and brick sump at PPU No. 3 and No. 4.

PPU NO. 3

PPU NO. 4

4.7.3 Adjusted contract rates / pro-rata rates

‘The said rates, where work is not of similar character and executed

under similar conditions as aforesaid, shall be the basis of rates for the

same, as far as may be reasonable…’ (Clause 25.1(b))

‘… if the omission vary substantially the conditions under which any

remaining items of work are carried out, the rates of such remaining

items shall be valued under rule (b)’ (Clause 25.1(c))

45

Page 18: Laporan Latihan Industri Bab 4

- These are the rates from the bills of quantities with adjustment for

differences between the varied work and the work priced but only so far

as may be reasonable.

- These adjusted contract rates are applicable for valuing:

a) Varied work not of similar character and executed under similar

conditions to the work in the bills of quantities.

b) Remaining items of work if they are to be carried out under very

different condition when part of the original work has been omitted.

Example 2 : Calculation of adjusted rate.

Assumptions :

Contract rate for 100mm x 100mm x 1.00 m long reinforced pre-cast concrete

lintel

= RM 10.00 / No.

The length of lintel is to be changed to 1.20m.

Pro-rata rate for 100mm x 100mm x 1.20 m long reinforced pre-cast concrete

lintel

= 1.201.00

x RM 10.00 = RM 12.00 / No.

46

Page 19: Laporan Latihan Industri Bab 4

4.7.4 Agreed rates

‘The said rates, where work is not of similar character and executed

under similar conditions as aforesaid,… failing a fair valuation thereof

shall be made by the S.O.. (Clause 25.1(b))

- These agreed rates are applicable for valuing :

a) Different work i.e. varied works which are different in character or

executed under conditions different from those included for in any

bill rates.

b) Remaining items of work if they are to be carried out under very

different condition when part of the original work has been omitted.

- To be used in the event where B.Q. rates and pro - rata rates are not

suitable.

- These rates normally consist of the cost plus a reasonable percentage for

profit.

- These rates are required to be agreed between the S.O. and the

contractor.

4.7.4 Day Work Price

- This method of valuation is normally used where the varied work cannot

be properly measured and values and a valuation at rates is not

practicable (example : Demolition work).

47

Page 20: Laporan Latihan Industri Bab 4

- To be eligible for payment, the contractor has to submit within 7 days after

the works have been done the following particulars to the S.O. for

verification :

a) Receipts as a proof for the amount paid

b) Particulars on :

- the workmen employed

- the plant employed

- the materials used

- The day work price can be :

a) The day work as priced by the contractor which is normally

included in the appendices to the contract document. It is important

for the S.O. to make sure that all items in this section are priced by

the contractor before the singing of the contract.

b) In the absence of (a), the actual cost of resources.

- The calculation of day work price includes the actual cost incurred by the

contractor and an allowance of 15% for profit.

48

Page 21: Laporan Latihan Industri Bab 4

4.8 Adjustment of Contract Sum

‘The amount to be added to or deducted from the Contract Sum in

respect…’ (Clause 29.0)

- The original contract sum has to be adjusted by taking into account the

following :

a) Fees and charges for supply of water, electricity, etc (Clause 6.2)

b) Variations (Clause 24)

c) Rectification of errors I the Bills of Quantities (Clause 26.3)

d) Fluctuation of price (Clause 30)

e) Payment of Prime cost sums (Clause 34)

f) Payment of Provisional sums (Clause 34)

g) Testing of materials and works covered up (Clause 35.2)

h) Loss and expense ( Clause 44)

i) Cost of disposal of fossil, etc. (Clause 64)

- The original contract sum has also to be adjusted by re-measurement of

provisional quantities (Clause 26.7).

49

Page 22: Laporan Latihan Industri Bab 4

4.9 P.A.M Contract 2006

- The relevant contractual provisions regarding Variations are as shown in

the table below :

Table 4.9.1 – Contractual Provisions.

4.9.1 Architect’s Instructions

- All instruction must be in writing and entitled Architect’s Instruction (‘AI’).

- Other written instructions (without title ‘AI’) become AI:

a) when confirmed in writing by contractor entitled “Confirmation of

Architect’s Instruction” (‘CAI’)

b) when confirmed in writing by Architect himself with an ‘AI’.

- A written instruction does not take effect unless the instruction is entitled

‘AI’ or ‘CAI’.

50

P.A.M. Contract 2006

Clause 2.0 – Architect’s instructions

Clause 11.0 – Variations, Provisional and P.C. sums

Clause 30.0 – Certificates and Payments

Page 23: Laporan Latihan Industri Bab 4

- If time of compliance is stated in ‘AI’ :

a) Time specified by Architect must not be less than 7 days from

receipt of ‘AI’.

b) Contractor must comply to AI within the given time.

c) If non-compliance by contractor – employer may engage other

person to carry out the work.

Employer may engage other

Receipt of AI person to execute work

Non-compliance by contractor

≥7 days

Figure 4.9.1.1 – Non compliance to AI by contractor.

51

Page 24: Laporan Latihan Industri Bab 4

Package Name:

To :

Attn : En. Roslan bin Sarip

Proceed as stated :

.............................................. Project Manager, IDMS Name in full : Date :

.............................................. Employer's Representative Name in full : Date :Copies :

* Delete whichever is not applicable

WCT Berhad

The Proposed Construction and Completion of Infrastructure Works For Medini Development, Iskandar Malaysia, Nusajaya, Johor Darul Takzim - Package Infra 3

No 12, Jalan Majistret U1/26, Seksyen U1, Hicom-Glenmarie Industrial Park, 40150 Shah Alam, Selangor.

Package No : MED1-INF03-CNTR-0003

From :

[ P ] P PROCEED WITH INSTRUCTIONE ESTIMATE COST/TIME EFFECT ONLYI INFORMATION ONLY

Summary Description:

Compliance with this Instruction is required in accordance with the Conditions of Contract

…………………………………………… E.R. Assistant Name in full : Date :

…………………………………………….. Contractor's Acknowledgement Name in full : Date :

Medini Iskandar Malaysia Sdn Bhd

MEDINI ISKANDAR MALAYSIA SDN BHD Company No. 782021-V

3.0 - EMPLOYER'S REPRESENTATIVE INSTRUCTION

E.I No : IDMS/MED/INFRA 3/2010/EI-_______

Under Clause 10 of Condition of Contract you are hereby instructed to effect the following :-

You are hereby instructed to construct and complete the additional structure of reinforced concrete gutter for all TNB sub stations as accordance to revised construction drawings and specification

1. Contractor 2. Contract Management & Administration 3. Project Team 4. Document Control

Ground Floor Seri Medini, No. 7, Persiaran Ledang Heights, 81560 Nusajaya, Johor

Example 3 : Variation Order (Copy from company)

52

Page 25: Laporan Latihan Industri Bab 4

53

Page 26: Laporan Latihan Industri Bab 4

Package Name Package No : MED1-INF03-CNTR-0003

DESCRIPTION :

TYPE OF E.I : (EI-P) PROCEED WITH INSTRUCTION.

CATEGORY : 1 - NEW SCOPE [ ] 3 - PROVISIONAL/PRIME COST SUM [ ]2 - OPTION PURCHASE [ ] 4 - CHANGE SCOPE [ √ ]

AMOUNT (RM) :

Element Qty Unit RM Rate RM Value

TNB Substations - Roof 90,054.80

90,054.80 Total Addition (RM)

DETAILS OF CHANGE

REASON FOR CHANGE

COMMENT ON COST OF CHANGETotal cost of nett addition = RM 90,054.80

IMPACT OF CHANGE ON PROJECT SCHEDULE

None

PMC/PMTPrepared by Reviewed and Checked by Recommended by

Name : PNFL / Melajasmiyati Md. Dali Name : Peter Tan Beow Teik Name : Designation : Consultant / VP,Cost & Contract Designation : VP, Project Designation : Date : Date : Date :IIBVerified By

VP, Project, MIMSB Director, Project & Infrastructure SVP, CMA Department Acting CEO, Medini, IskandarName : Norashiken bt Ibrahim Name : Wong Chan Thong Name : Mohd Azmi bin Hitam Malaysia Sdn. BhdDate : Date : Date : Name : Ir. Khairil Anwar bin Ahmad

RM90,054.80

4.0 - EMPLOYER's REPRESENTATIVE INSTRUCTION RECOMMENDATION

* * * THIS IS AN INTERNAL DOCUMENT ONLY * * *

The Proposed Construction and Completion of Infrastructure Works For Medini Development, Iskandar Malaysia, Nusajaya, Johor Darul Takzim - Package Infra 3

E.I No : IDMS/MED/INFRA 3/2010/EI-_______

To carry out additonal earthwork at Road C, Road F and Road G with superelevations and normal crossfalls all as shown in the drawings.

Description

Nett additional reinforced concrete structure of gutter for all TNB sub-station

The size increase due to existence of pitch roof. Original gutter wall is 380mm height. Revised construction drawings is 1200mm height.

The design changed due to cater the run-off water and aesthetic value.

54

Page 27: Laporan Latihan Industri Bab 4

Package Name : Package No : MED1-INF03-CNTR-0003

Variation Order No: IDMS/MED/INFRA 3/2011/VO-003

EI No. closed out : IDMS/MED/INFRA 3/2010/EI-__

To : From :

81560 Nusajaya,

Attn : En. Roslan bin Sarip

VO Title :Additional Structure of Reinforced Concrete Gutter for all TNB Sub-Stations as Accordance to Revised Construction Drawings and Specification.

VO Detail :The size increase due to existence of pitch roof. Original gutter wall is 380mm height. Revised construction drawings is 1200mm height.

Employer's Representative Instruction closed out : IDMS/MED/INFRA 3/2010/EI-__

Element Unit RM RateOmission Addition

SOW 14 : TNB Substations - Roof

(115,168.20) 205,223.00

(115,168.20) 205,223.00

90,054.80

Schedule Impact : No time impact

Contractor Employer's's Representative/ERAAcceptance Authorisation:

Name in Full : Name in full : Date : Date :

Copies to :1. Contractor 4. Employer's Representative/ ERA2. Contract Management & Administration 5. Finance3. Project Management/ Project Manager 6. Document Control* Delete whichever is not applicable

MEDINI ISKANDAR MALAYSIA SDN BHDCompany No. 782021-V

5.0 - VARIATION ORDER

The Proposed Construction and Completion of Infrastructure Works For Medini Development, Iskandar Malaysia, Nusajaya, Johor Darul Takzim - Package Infra 3

WCT Berhad Medini Iskandar Malaysia Sdn. Bhd.

Nett additional reinforced concrete structure of gutter for all TNB sub-station

No 12, Jalan Majistret U1/26, Seksyen U1, Ground Floor,Hicom-Glenmarie Industrial Park, No. 7 Persiaran Ledang Heights40150 Shah Alam, Selangor.

Johor Darul Takzim.

The Employer hereby gives to the Contractor this Change Order for, and the Contractor agrees to provide the material and perform the work describedherein, in accordance with all of the terms Contract unless otherwise expressly stated herein.

RM Value Description

Not valid until signed by Employer's Representative. Signature of the Contractor indicates agreement herewith, including any adjustment in the Contract Sum and the Date for Completion or Section. This Variation Order is the entire claim in respect of the above works and/or material supplied.

Total

Nett Addition :-

55

Page 28: Laporan Latihan Industri Bab 4

To : Employer's RepresentativeFrom : Project TeamDate : 15-Apr-2011

Package No. :

Package Name :

Variation Order No. : IDMS/MED/INFRA 3/2011/VO-003

VO Description :

VO Amount : RM90,054.80

We hereby recommend the approval of the above Variation Order for the following reasons:

SUMMARY OF CONTRACT STATUS

RMa. Contract Sum (plus 5% service tax) 284,539,383.06 Cat 1234 Cat 5 Cat 1234 Cat 5b. Approved VOs 112,083.00 112,083.00 0.00 0.04% 0.00% 0.04%c. Pending VOs 32,478.18 32,478.18 0.00 0.01% 0.00% 0.01%d. Previous VOs (b+c) 144,561.18 144,561.18 0.00 0.05% 0.00% 0.05%e. This VO 90,054.80 90,054.80 0.00 0.03% 0.00% 0.03%f. Total All VOs (d+e) 234,615.98 234,615.98 0.00 0.08% 0.00% 0.08%New Contract Sum 284,773,999.04

Details Of Change

Reason For Change As per MCLD's requirement changed due to cater the run-off water and aesthetic value.

Comments On Cost Of Change Total cost of nett addition as per summary breakdown.

Impact On Design/Project Schedule None

Instruction Closed Out : IDMS/MED/INFRA 3/2010/EI-__

With the issue of this Variation Order, the following Employer's Representative Instruction is closed-out : IDMS/MED/INFRA 3/2010/EI-__

Please indicate your approval to issue this Variation Order by signing the attached Variation Order form.PMC/PMTPrepared By Reviewed & Checked By Recommended by

Name : PNFL / Melajasmiyati Md. Dali Name : Peter Tan Beow Teik Name : Designation : Director / VP, Cost & Contract Designation : VP, Project Designation : Date : Date : Date :IIBVerified By

VP, Project, MIMSB Director, Project & Infrastructure SVP, CMA Department Acting CEO, Medini, IskandarName : Norashiken bt Ibrahim Name : Wong Chan Thong Name : Mohd Azmi bin Hitam Malaysia Sdn. BhdDate : Date : Date : Name : Ir. Khairil Anwar bin Ahmad

Details as per enclosed drawing, Contract Drawings No. : RB1689/T-INF-3/TNB004, RB1689/T-INF3/TNB/S/DCA1/03, RB1689/T-INF3/TNB/S/DCA1/04, RB1689/T-INF3/TNB/S/DCA2/03, RB1689/T-INF3/TNB/S/DCA2/04 and Construction Drawing No. : RB1689/C-INF3/TNB/S/DCA1/03, RB1689/C-INF3/TNB/S/DCA1/04, RB1689/C-INF3/TNB/S/DCA2/03, RB1689/C-INF3/TNB/S/DCA2/04.

The Proposed Construction and Completion of Infrastructure Works For Medini Development, Iskandar Malaysia, Nusajaya, Johor Darul Takzim - Package Infra 3

The size increase due to existence of pitch roof. Original gutter wall is 380mm height. Revised construction drawings is1200mm height.

6.0 - VARIATION ORDER RECOMMENDATION * * * THIS IS AN INTERNAL DOCUMENT ONLY * * *

1. New Scope [ ] 2. Option Purchase [ ] 3. Provisional & PC Sum [ ] 4. Changed Scope [ √ ] 5. Remeasurement of Prov.Quantities [ ]

MED1-INF03-CNTR-0003

Additional Structure of Reinforced Concrete Gutter for all TNB Sub-Stations as Accordance to Revised Construction Drawings and Specification.

In accordance with the following and the IIB's Limits of Authority in force at the time of writing this memo, this Variation Order is within your limit of Authority.

Breakdown of VO Total % of Contract Sum RM %

56

Page 29: Laporan Latihan Industri Bab 4

57