EINRIP Project Handover Road Safety Audits Project PHO RSA Closing Meeting, Makassar

30 April 2012

David Williamson

Road Safety Auditor

VicRoads International

Page 2: Ess 01 & ess-02 closing meeting

2

South Sulawesi ESS-01 : Sengkang – Impa Impa – Tarumpakkae

Construction in progress in accordance with original design plans

Road safety audit (RSA) of detailed design plans conducted in June 2007

Design incorporates some of the recommendations of the RSA

Work still to be completed: • Shoulder sealing • Traffic islands at two major intersections • Guardrail installation • Pavement markings

Page 3: Ess 01 & ess-02 closing meeting

3

Delineation of curves

Page 4: Ess 01 & ess-02 closing meeting

4

Delineation of hazards

Page 5: Ess 01 & ess-02 closing meeting

5

Delineation of hazards

Page 6: Ess 01 & ess-02 closing meeting

6

Removal of hazards

Page 7: Ess 01 & ess-02 closing meeting

7

Intersections – Jl. Bau Baharuddin (0+170)

Existing island to be

remove and new island

to be constructed as per

the design

Page 8: Ess 01 & ess-02 closing meeting

8

Intersections – Jl. Rusa (1+300)

Page 9: Ess 01 & ess-02 closing meeting

9

Intersections – Jl. A Baso (3+250)

Page 10: Ess 01 & ess-02 closing meeting

10

Speed limits

Page 11: Ess 01 & ess-02 closing meeting

11

Signs

Page 12: Ess 01 & ess-02 closing meeting

12

South Sulawesi ESS-02 : Bantaeng – Bulukumba

Construction is complete - PHO 12 March 2012

Variation order for additional road safety works based on the RSA of the detailed design has been prepared and is awaiting approval

Page 13: Ess 01 & ess-02 closing meeting

13

Guardrail – terminals

Page 14: Ess 01 & ess-02 closing meeting

14

Guardrail – connection at bridges

Page 15: Ess 01 & ess-02 closing meeting

15

Guardrail – overlapping of panels

Page 16: Ess 01 & ess-02 closing meeting

16

Guardrail – connection at bridges

Page 17: Ess 01 & ess-02 closing meeting

17

Guardrail – length

Page 18: Ess 01 & ess-02 closing meeting

18

Intersection at Sta. 6+100

Page 19: Ess 01 & ess-02 closing meeting

19

Intersection at Sta. 24+090

Page 20: Ess 01 & ess-02 closing meeting

20

Roadside hazards

Page 21: Ess 01 & ess-02 closing meeting

21

Parking lane at the market (4+375)

Page 22: Ess 01 & ess-02 closing meeting

22

Obscured signs

Page 23: Ess 01 & ess-02 closing meeting

23

End of project at Bulukumba

Page 24: Ess 01 & ess-02 closing meeting

24

Terima Kasih