Upload
tristan-wiggill
View
83
Download
0
Embed Size (px)
Citation preview
ROLE OF HIGH-LEVEL PROJECT PROFESSIONALS’ PERCEPTIONS ON QUALITY PROCESSES IN DIRECTING THE INVESTIGATION OF CAUSES
OF PREMATURE PAVEMENT DISTRESSES: AN EXPLORATORY STUDY
M B Mgangira, S Das and J O’Connell
M B Mgangira, Dr.-Ing., Pr. Eng
Southern African Transport Conference 2016 CSIR International Conference Centre
4 July 2016
Introduction
IntroductionWhy?
Introduction
IntroductionOccurrence of premature
pavement distresses
Introduction
Longitudinal Cracking
Introduction
Severe Rutting
Introduction
Good practice calls forinvestigation to find thecauses
Extent of investigation depends on the client requirements
Introduction
Who done it?
Introduction
Causes
Combination of failuresDesign errors
Inadequate quality control, testing and procedures
Inadequate construction supervisionPoor communication
Introduction
Causes of errors
UnawarenessInexperience
Mistakes such as noncompliance
Slips and lack of attention
Thank you
Context
Consequences of errors only manifest themselves long after
they occurred
They reside in a system until they become an actual failure
= PATHOGENES
Busby and Hughes (2004)
Context
Which way to find Who done it?
ContractorConsultant
Thank you
Context
Forensic investigation
Objective Scientifically conducted Systematically recorded
Thank you
Context
Phases of the investigation
Data collection Analysis Solutions and recommendations
Thank you
Data collection: Test Pit
Context
© CSIR 2014
Context
Findings
Thank you
Context
Consequences of errors only manifest themselves long after
they occurred
They reside in a system until they become an actual failure
= PATHOGENES
Busby and Hughes (2004)
Context
Can perceptionof high-level professionals provide an indication?
Thank you
Process
High-level professionals interviewed and responded to a
questionnaire
Contractor representatives Consultant representative Owner
Thank you
Process
Different attitudes towards the survey
Overall rating of project A75% rated project as Good
Thank you
Process
Overall rating
© CSIR 2014
Responses Project A
Item Response (%)
Strongly Agree
Agree Not Sure (Missing)
Disagree Strongly Disagree
Construction Supervision Consultant communicated project specification to the Contractor correctly
12.5
75
12.5
0
0
Change in scheduling was communicated to Contractor in time
25
50
12.5
12.5
0
There was regular communication between Construction Supervision Consultant and Contractor’s engineer
25
50
(12.5)
0
12.5
Communication
© CSIR 2014
Responses
Item Response (%)
Strongly Agree
Agree Not Sure (Missing)
Disagree Strongly Disagree
Regular in-situ testing was carried out during the duration of the project
12.5
75
0
0
12.5
Quality check for materials was NOT done routinely
0
0
12.5
50
37.5
Laboratories that conducted quality checks in this project can be relied upon
37.5
62.5
0
0
0
Laboratory reports can be influenced
12.5
12.5
50
25 0
Quality of testing
© CSIR 2014
Responses
Item Response (%)
Strongly Agree
Agree Not Sure (Missing)
Disagree Strongly Disagree
The General Specifications of the project were understood by the contractor
12.5
50
0
37.5
0
The project tender documents were understood by the contractor
0
50
0
25
25
Contract documentation
© CSIR 2014
Responses Project B
Perception item Contractor Road Authority Consultant
Cause of the Defect
External environment (climate, traffic loading)
Poor workmanship, design, materials
Poor workmanship / design / materials
Project Specifications
Project specifications insufficiently strict to maintain performance
Adequate Adequate
Skill Sets Own skills set was adequateQuestioned the skills set of the Road Authority
Own skills set was adequate. Questioned the skills set of the Contractor
Own skills set was adequateQuestioned the skills set of the Contractor
Indicators
Understanding of GeneralSpecifications
Lack of clarity of information in Special Specifications
Or poorly compiled specifications
Indicators
Linkage between perceptionand extent of awarenessof quality processes during project execution
identification of root causesof premature pavement distress
and
Thank you